Cadent Gas major roadworks project

Road closures in Seven Sisters/West Green Road, May to September 2024

Cadent Gas will soon begin a major project to improve the reliability of its network for customers across north London.

Cadent will close West Green Road for about 10 weeks from May to July 2024. 

Traffic and bus diversions will be in place.

While Cadent Gas understands the disruption this will cause and are working closely with us to minimise this as much as possible, the works are vital to ensure their network remains reliable to avoid any loss of heating and hot water to customers across North London.

More information and regular updates are available on the Cadent Gas website.

We will also provide regular updates in our weekly e-newsletter Haringey People Extra and on our social media channels. 

Project dates

Cadent Gas will start the project on Tuesday 7 May. The 3 phases of work should take approximately 19 weeks, until Friday 13 September.

Road closures

Cadent Gas are closing the following roads:

  • West Green Road between Westerfield Road and Portland Road, and High Road from 7 May to 21 July
  • Westerfield Road and Suffield Road at their respective junctions with West Green Road, with access only via Seven Sisters Road

A diversion will be in operation directing traffic travelling between Turnpike Lane and Seven Sisters to use Green Lanes and Seven Sisters Road.

Cadent Gas will also close part of the Westerfield Road Car Park throughout the project for storage and welfare facilities.

Work near the Seven Sisters tube station exit will take place in August and September.

Other traffic management measures 

For the duration of the works, the following traffic measures will be put in place to assist with traffic flow in the area: 

  • Westerfield Road will be made 2-way for resident parking and to allow customers to West Green Road businesses to access and park locally
  • Suffield Road will also be made 2-way for resident parking
  • Portland Road/West Green Road junction will be traffic signal controlled
  • Temporary changes will be made to the Bruce Grove West Green and St Ann’s LTNs – please find further details below

Bus diversions and stop closures

Transport for London will operate the following bus diversions during this project.

Route 41 and N41 towards Tottenham Hale

From West Green Road at the junction with Spur Road, left Spur Road, bear right onto Philip Lane, right Townhall Approach Road, right High Road, left Broad Lane to line of route.

Route 41 and N41 towards Archway

From Broad Lane at the junction with High Road, right High Road, left Philip Lane bear left onto Spur Road, right West Green Road to line of route.

Seven Sisters Station bus stop E (West Green) and D (High Road) will be closed.

The Seven Sisters tube station north-facing entrance (towards the junction with West Green Road and High Road) will also be closed for the duration of the works.

All the other entrances and exits to Seven Sisters will remain open as normal.

Changes to low traffic neighbourhood (LTN) trials

LTN camera-controlled enforcement will be temporarily suspended on the following roads for the duration of the works.

Bruce Grove West Green LTN:

  • Mount Pleasant Road (northbound no-entry lifted, southbound filter remains operational)
  • The Avenue
  • Broadwater Road (northbound filter lifted, southbound filter remains operational)

St Ann’s LTN:

  • La Rose Lane

Stay in the know

More information and regular updates are available on the Cadent Gas website.

If you have any questions on the project, you can get in touch with the Cadent Gas community relations team.

Contact Cadent Gas community relations team