Notifications for garage works, re-roofing of house/flats, erection of new house/flat/maisonette

Part of: Key notification stages for inspection

Inspections need to take place while items are still completely visible.

Notifications for garage conversion to habitable room

  • Stage 1 – Commencement – may be combined with stage 2
  • Stage 2 – Inspect excavation for infill wall/window to replace garage door
  • Stage 3 – Check DPC in wall and DPM to floor
  • Stage 4 – Check new floor construction including Insulation and new drains (if needed)
  • Stage 5 – Check New Insulation to Walls and roof with any associated roof void ventilation
  • Stage 6 – Check the adequacy of ventilation to the room and the adequacy of means of escape in the event of a fire
  • Stage 7 – Completion - may be combined with stage 6 if all is okay

Notifications for re-roof of house or block of flats

  • Stage 1 – Commencement – may be combined with stage 2
  • Stage 2 – Inspect roof timbers after removal of original covering
  • Stage 3 – Check insulation upgraded, felt underlay provided, finish of tiles/slates, provision of flashings
  • Stage 4 – Completion – may be combined with stage 3 if all is okay

Notifications for the erection or extension of a single-storey garage or carport

  • Stage 1 – Commencement – may be combined with stage 2
  • Stage 2 – Inspect excavation for foundations
  • Stage 3 – Check DPC in Wall and Fire safety provisions (if any)
  • Stage 4 – Check (if any) new drains
  • Stage 5 – Check roof timbers/steels/lintels
  • Stage 6 – Completion – may be combined with stage 5 if all is okay

Notifications for the erection of a new house, flat or maisonette

  • Stage 1 – Commencement – may be combined with stage 2
  • Stage 2 – Inspection of new foundations and drain pipes
  • Stage 3 – Inspection of oversite - may be combined with stage 4
  • Stage 4 – Inspection of damp-proof membrane for new floor and any tanking where needed
  • Stage 5 – Inspection of new walls dpc and below ground drain pipes
  • Stage 6 – Inspection of upper floor steels and timber floor joists
  • Stage 7 – Inspection of roof timbers, new beams and lintels and roof void ventilation
  • Stage 8 – Inspection of Drainage connections above ground including witness of drain tests
  • Stage 9 – Completion - can be combined with stage 8 if all is okay. Items usually inspected include automatic smoke detectors and alarms, fire doors, and emergency lighting units (if any) and receipt of installer certificates/Sound Test/SAP/EPC etc where applicable